We have extensive experience with water resources projects.

Argo Drain Sub-Basin Facility Project

​The project includes construction of underground diversion facilities to capture storm water from LAWA Airside Operations Area and LA County storm drains, conveying and pumping the water through two tunnels using the jack and bore method.  Water is collected from the Argo flood channel located inside LAX and from various LA County storm conveyance facilities. The stormwater is captured and conveyed in tunnels to a deep underground pump station that lifts the water up to an 8-million-gallon underground tank with an open bottom to allow for infiltration and recharge of groundwater aquifer. Mr. Walid Azar is overseeing the project and providing change management oversight, schedule oversight, review of payment requests, review of RFIs / Submittals, and assistance on resolving technical issues.

 

Construction Value: $37M

  

Machado Lake, City of L.A.

This project is being implemented implemented by the City of Los Angeles Department of Public Works Bureau of Engineering (BOE), in collaboration with the Bureau of Sanitation and the Department of Recreation and Parks. The objective is to rehabilitate Machado Lake to clean the lake of pollution and sediments, use highly treated recycled water (sewage treated by microfiltration and reverse osmosis) to fill the lake when stormwater flows are not adequate and give the Community an improved and more sustainable park to enjoy.

Service Provided: Onsite construction management support services to the BOE including
site coordination, budget & schedule, control, estimating, change order management, claims analysis, document control and partnering.

 

Construction Value: $75M

  
Echo Park, City of L.A.

This project was implemented by the City of Los Angeles Department of Public Works Bureau of Engineering (BOE), in collaboration with the Bureau of Sanitation and the Department of Recreation and Parks.The objective is to rehabilitate Echo Park Lake to remedy its storm water pollution problem, meet the State's water quality standards, and give the Echo Park community an improved and more sustainable lake to enjoy.

Service Provided: Onsite construction management support services to the BOE including change negotiations, coordination with various stakeholders, cost estimating, and evaluation of various scenarios for critical soil remediation studies.


2013 AWARD: Engineering News-Record (ENR)
Best Water/Environment Project (So. CA.) award
.


Construction Value: $27M

  